What has to be true by the next board meeting for the go-live date to hold?
A go-live date is a forecast, and it rests on a few conditions that either hold or do not. Asking for the conditions turns a status colour into something the board can check at the next meeting.
What a strong answer includes
- Names three or four specific conditions, such as the results of the data migration rehearsal and the share of critical business processes fully tested and passed.
- Makes each condition a test that can fail, such as “the final rehearsal reconciles every balance and finance signs it off”, not an activity with a date, such as “testing complete by March”.
- Gives each condition an owner and a date, says which ones the board will know about by its next meeting, and which is weakest today and why.
- Puts a cost on a delay, including running the old system for longer, and says how much contingency is left.
- Says who makes the call to move the date, when the board would hear, and what the fallback is if go-live fails.
What a weak answer sounds like
- “We are tracking green overall.”
- “The team is working through testing, data cleansing and training.” A list of activities, with no condition that would change the date.
- “The implementation partner is confident in the date.”
If the answer is weak, ask
Which of those is most at risk today, and who decides to move the date?
Red flags
- The status has been green for months while milestones quietly move.
- The go-live criteria have been softened since testing began, or were written by the implementation partner rather than the business.
- Data migration has not yet been rehearsed end to end on a full copy of the data.
- The conditions change from one board meeting to the next.
Ask for in writing
- The go-live criteria on one page, with the owner, date and current status of each.
- A one-page testing summary showing the share of tests passed by business process, and the open defects that would stop go-live.
- Cost to complete against budget, with contingency used and remaining.
- The latest independent assurance report on the programme, with management's response.